INNOVATIVE AIRFIELD PAVEMENT DESIGN
Ooms Avenhorn Holding bv, Senior Manager
Research & Development, Scharwoude,
SUMMARY:
Most of the economic activities around the
world are located in delta areas along coasts. A common problem for these
areas is that they lack space, especially to expand or build airports. This
implies that if there is space available, it should be used, irrespective of
the quality of the existing soil. To enable design and construction of
economic (cost-effective) airfield pavements which are free of maintenance
for a long period of time, the use of three-dimensional finite element
simulations is necessary. Ooms Avenhorn Holding has utilized this approach
for an alternative design for the Amsterdam Airport Schiphol 5th
runway project. The result was a 'balanced' semi-rigid pavement design
consisting of polymer modified asphalt layers on precracked cement treated
base layers, in which the life of the asphalt on top and in between the
(planned!) base cracks was 'matched'.
Keywords:
airfield pavements, design, maintenance-free, reflective cracking,
settlements.
1. INTRODUCTION
Ooms Avenhorn Holding was invited by Amsterdam
Airport Schiphol to develop an innovative alternative airfield pavement
design concept for its new 5th runway. This new runway is
urgently needed for this Airport, which is one of the European hubs, because
of the limited capacity of the existing four runways, due to noise and wind
restrictions. Given its economic importance, it is clear that this new
runway should be free of maintenance for a long period of time. This
objective is a hard one, especially because Schiphol is located in the
western part of the Netherlands, where the soil consists of layers of peat
and clay up to a depth of 20 m below ground level. More specifically,
Schiphol is located roughly 5 m below sea level at the bottom of a former
lake; the lake was impoldered in the 19th century and used for
agriculture until in the 1920's the development of Schiphol started. Typical
soil conditions in the Schiphol area are about 7 m of peat/clay on top of
so-called Pleistocene (quite stiff) sand layers. Interesting to note is that
in the 1950's, when jet airplanes were introduced in commercial aviation,
Schiphol constructed so-called sandwich type pavement structures, consisting
from top to bottom of: asphalt, unbound granular material and concrete [1].
All in all, from the foregoing it has become clear that the Ooms company was
faced with a tough design challenge, considering the expected widespread use
of triple gear new large aircraft in future and the strict demands on the
runway profile (uneven settlements!).
In this paper an overview is given of the
innovative aspects of the Schiphol 5th runway design made by Ooms
Avenhorn Holding. It will also become clear how finite element analyses were
utilized to verify the proposed alternative when it will be subjected to
effects of aircraft traffic, temperature variations and (uneven)
settlements. All these types of loadings will or can be activated during the
required 40 years design period; temperature variations also in the phase of
construction.
2. DESCRIPTION
OF RUNWAY CROSS-SECTION
A sketch of the proposed cross-section of the
runway is shown in figure 1. The selected type of structure (semi-rigid)
combines in an economic (cost-effective) way the advantage of a flexible
structure (no cracking due to settlements) with the advantage of a stiff
structure (distributing aircraft loadings to a large subsoil area). The thin
asphaltic mixture between both cement treated base layers guarantees a
frictional interface between these layers for a long period of time;
temperature variations (shrinkage/expansion) and uneven settlements cannot
'separate' these layers. The latter would of course be detrimental for the
required flexural stiffness of the entire pavement structure.
Figure 1 Sketch of
Proposed Runway Cross-Section
Use was made of the sand, already needed to
shorten the consolidation process in the underlying soil, to prepare the
lower part of the cement treated base. This base layer was chosen as thick
as possible with the current stabilization equipment, in order to maximize
the ratio between the obtained flexural stiffness and the investment. The
top part of the cement treated base consisted of a plant made mixture of
recycled masonry and asphalt. In both cement treated layers a cement
percentage of 10 (by weight) was planned.
The bituminous part of the entire runway
structure (the upper 200 mm) is from bottom to top composed of a 30 mm thick
special type of asphalt mixture (Thermifalt: composed with 8 % Sealoflex®
SFB5-90 bitumen), a reinforcing system, three each 50 mm thick layers
of 'standard' polymer modified asphalt with jet fuel resistant Sealoflex®
bitumen and high-quality aggregates (Grauwacke); the wearing course is
a specially developed 20 mm thick jet fuel resistant layer called Novachip
Durable Antiskid Pavement Layer (DAPL).
The precracking pattern (4 by 4 m slabs) in
both cement treated layers and the way in which the reinforcing system is
placed on top of the Thermifalt, are presented in figure 2. The reason to go
for the diagonal type of precracking pattern, which makes an angle of 45°
with the runway axis, is that compared to the traditional rectangular
pattern (value of 0°), the traffic and temperature induced displacements are
then 'separated'.

Figure 2 Overview of
Precracking and Reinforcement Pattern
The reinforcing system is composed by means of
the product GlasGrid 8512 which has a stiffness of 8000 N/mm; as a glue with
the surrounding asphalt, 1.2 kg/m2 of jet fuel resistant
Sealoflex® polymer modified bitumen was proposed. The system is
placed only at the 30 m wide central (trafficked) zone of the runway. The
reinforcing product is of course layed down only on top of the cracks in the
cement treated base layers; this in a width of 1.5 m. Laboratory pullout
tests have shown that this anchorage length is adequate.
In order to reduce maintenance because of
Foreign Object Damage (FOD) as much as possible, in the touch-down zone, the
top and middle asphalt layer would be glued via spraying an amount of 1.0
kg/m2 of Sealoflex® jet fuel resistant polymer
modified bitumen. The interface between these layers is at a depth of 70 mm
below the surface. Laboratory interface shear testing (displacement rate of
5 mm/s) at several temperatures (ranging between -10 and +40 °C) showed that
compared to a standard tack coat with 0.3 kg/m2 of plain
emulsion, a higher shear strength and toughness could be obtained, for
similar shear stiffnesses; the polymer interface also gave less variability
in strength and toughness.
3. TRAFFIC LOADS
3.1 Base, subbase
and subgrade layers
Use was made of the Australian airfield
pavement design program called APSDS [3], in order to estimate the damage
caused by the mix of aircraft traffic during the whole 40 year service
period. Amsterdam Airport Schiphol had specified that during this period
amongst small to medium ones, about 4 million heavy wheel loads (between 25
and 30 tonnes) belonging to the aircraft types B747-400, B777, MD11 and NLA
(new large aircraft such as the A380) would pass. Despite the fact that in
this so-called multi-layer program, the entire pavement structure is
modelled as having infinite layers (in the horizontal direction), whereas in
reality the cement treated base layers are precracked, it was still applied
since by utilizing this quick approach, the most critical parts of the
entire pavement structure (the cement treated base layers) are checked on
the safe side; in reality the bending (flexural deformation) of these layers
will be less since the 4 by 4 m slabs will deflect individually (move
downwards). A nice aspect of APSDS is that the overall influence of the
entire mix of aircraft, as specified by Amsterdam Airport Schiphol, and the
effect of the degree of lateral wander is fully taken into account, thereby
saving engineering time and increasing accuracy.
It is clear that for all materials (layers),
stiffness moduli and damage laws had to be inputted in APSDS. These damage
laws are of the type: N = (ef
/e)r,
where N represents the number of traffic load repetitions required to crack
the asphalt surfacing, respectively the cement treated base layers or deform
the sand subbase, respectively the peat/clay subsoil. The asphalt values for
ef
and r were based on Schiphol experience, the base layer values for these
parameters were obtained from Ooms initiated laboratory testing and the
sand/soil values for ef
and r came from FAA-literature.
For the thin asphaltic layer located in
between the cement treated base layers (the interface-asphalt mixture), the
parameter ef
was obtained from a Mohr-Coulomb law established for this purpose (see
figure 3). The parameter r for this material could be obtained from cyclic
tensile tests and by extrapolating cyclic aggregate interlock tests [2]. To
be able to analyse the shear induced fatigue of the interface-asphalt layer
in APSDS, a shear damage law was especially created for the Ooms alternative
by Wardle [3].
In a later stage of the design process, also
tensile stress (st)
based damage laws for the cement treated base layers were incorporated.
These were log N = 8.865 - 3.166 * st
for the stabilized mixture of aggregates and log N = 12.0 - 12.0 *
st
for the stabilized sand.

Figure 3 Obtained
Mohr-Coulomb Relationship for Interface-Asphalt
Examples of computed distributions of the
Cumulative Damage Factors along the width of the runway after 30 years of
aircraft traffic, are given in figures 4 and 5; this for the upper cement
treated base layer as well as for the interface-asphalt layer (note that a
CDF-value of 1 implies failure of a specific pavement layer!). It can be
observed that damage is concentrated at roughly 5 m from the centerline. It
is noted that the whole front gear or the whole rear gear of all planes were
taken into account (so for each case both the wheels at the left and right
of the centerline), see figure 2.

Figure 4 Computed CDF-Distribution of Upper Cement Treated Base Layer
Figure 5 Computed
CDF-Distribution of Interface-Asphalt Layer
It is recalled that use would be made of the
already present sand, to prepare in-situ the lower cement treated base
layer. The well-known drawback of an in-situ approach is that quite a lot of
variability in mechanical properties can be expected to be found. To
quantify this aspect, the Ooms company carried out a small study. In total
16 cores were taken from an industrial site, which was build-up with sand
placed by wet transport (pipelines) and stabilized in-situ with modern
equipment to a depth of 500 mm. Before testing, the cored cylinders were
divided in three (top/middle/bottom). By performing acoustic stiffness and
subsequent compressive strength testing in the laboratory, it was found that
variability along the site was much more predominant than in depth
(top/middle/bottom of each cylinder). This implies that the cement mixing
process and the compaction quality with depth are no issues with respect to
variability. Important with respect to this are: the grading curve of the
sand and the differences in compaction (number of roller passes) along the
site. With respect to the latter it can be mentioned that modern rollers
with compaction monitoring equipment can be very useful. Interesting to note
is that the following relationship was found between the acoustic stiffness
and the compressive strength values: Eacoustic = 4300 *
sc0.65
(units MPa), as measured after a period of 28 days after construction. Given
the nature of this relationship, it is clear that the acoustic stiffness
showed less variability than the compressive strength (the coefficients of
variation were roughly 25 %, respectively 35 %).
Based on the foregoing it was felt that enough
understanding was generated to come up with a minimum base material
stiffness to be utilized for the Schiphol 5th runway design
process (in the latter situation, sand was planned to be transported by
trucks, which causes less variability due to the phenomenon of segregation;
furthermore, a higher cement percentage would be used). The value for the
design stiffness was also based on the experience that investigations on
laboratory prepared specimens had revealed that the so-called dynamic
stiffness as obtained by means of mechanical servo-hydraulic testing (the
parameter to be used for the design process!) was roughly half the acoustic
one. The latter finding has interesting practical implications since an
acoustic test can be done easily in the field on cored cylinders.
All in all, it could be concluded that it will
take at least 30 years to crack the base layers due to traffic induced
fatigue. It can be estimated that before this type of cracking will become
visible at the asphalt surface via the well-known alligator skin shapes,
certainly another period of 10 year passes [4]. This also because at several
levels (heights) in the pavement, extra resistance to upward propagation of
the base fatigue cracks is build-in (the porous interface-asphalt, the
Thermifalt and the reinforcing system).
3.2 Asphalt
During each passage of an aircraft, stress
concentrations will be generated in the bituminous surfacing just on top of
the cracks (notches) in the cement treated base layers. These will cause the
reflection of the precracking pattern into and through the surface of the
wearing course. This phenomenon of reflective cracking has been generating
lots of discussions and debates in the past. As described in detail by de
Bondt [2], the only way in which this special type of cracking can be
investigated, is via the finite element method. A short overview of the work
done for the Schiphol 5th runway project on this, is described
below.
The mesh prepared for the CAPA-3D traffic
loading analyses, is presented in figure 6; the program CAPA-3D is the
PC-based version of the finite elements program INSAP which is under
development at the section Structural Mechanics of the Department of Civil
Engineering of Delft University of Technology [5]. The 'traffic' mesh
consisted of 5265 elements and represents a part of the runway having four
by three cement treated slabs (this is 16 m in the longitudinal direction by
12 m in the transverse direction). Because of symmetry only half of this
part of the runway had to be inputted. The mesh itself is thus 16 by 6 m.
The peat/clay layers had a thickness of 7 m. Since at this depth the
relatively stiff Pleistocene sand layers are located, the nodes at the
bottom of the mesh were fixed in all directions. The vertical edges were not
restrained. Potential load transfer in the cracks was not taken into
account, since it has been found that in the long run this hardly exists
anymore [2]. The stiffness (Young's modulus) of the asphalt layers was set
equal to 2500 MPa; the shear stiffness of the interface between the asphalt
and the base to 0.5 (N/mm)/mm2. Based on laboratory testing, the
Young's modulus of the cement treated aggregates (upper base layer) was set
equal to 8500 MPa; a value of 4500 MPa was used for the cement stabilized
sand layer. The stiffness of the interface-asphalt was 2000 MPa. Values for
the sand subbase and the (existing) soil were 100 MPa, respectively 30 MPa.

Figure 6 Mesh used for
the Simulation of Aircraft Loadings
The effect of two positions of a single wheel
load were examined; one when the vertical load (magnitude 30 tonnes,
distributed on an area which is 600 mm long and 400 mm wide) is just next to
the base crack (notch), as denoted by P, and one when the load is placed
centered with respect to the base crack (denoted by Q). Unfortunately, not
enough time was available to examine if other load positions would perhaps
be worse. Given the large distances between aircraft wheels, as compared to
the total asphalt thickness, only a single wheel was taken into account.
Wheel load interaction was in this case thought to be of minor importance.
From computed profiles of vertical
displacements along the pavement surface, it became clear that the
off-centered load position caused the largest degree of flexure. Important
to mention is that only in the top part of the base crack, compressive
actions along the crack occur. This implies that the use of a material (in
this case cement stabilized sand) in the lower base layer, which does not
have the potential for aggregate interlock (only for dry friction along the
crack faces), is not a disadvantage.
Computed tensile strains in the bituminous
surfacing are given in figure 7. It can be observed that the effect of the
discontinuity (notch), the presence of large tensile strains, is limited to
the bottom part of the asphalt. This is the reason that the (relatively
expensive) Thermifalt mixture was planned only at this location.
Figure 7 Computed
Principal Strains along Asphalt Cross-Section
Although the incorporation of the flexible and
tough Thermifalt increases the lifetime of the bituminous surfacing, it can
be deduced that it will be less than the required 4 million heavy wheel load
passages [4]. In other words, it is inadequate. In order to solve this
problem, a reinforcing system was thought to be used on top of the
Thermifalt. Its effectiveness has been assessed as follows: from the
computed displacements at the level (height) of the top of the base cracks
(= bottom of asphalt layers), it can be derived that during a wheel passage
a relative vertical movement at the edges of the crack of about 0.1 mm
occurs. By using this slip value, it can be deduced, based on numerical
crack propagation studies carried out in the past by de Bondt [2], that a
properly anchored reinforcing product with a stiffness (EA)rf
equal to 8000 N/mm, can increase the lifetime of the remaining (uncracked)
170 mm thick bituminous surfacing by a factor of roughly two. To achieve
this durable anchoring, a polymer modified tack coat (with Sealoflex®
bitumen) was planned to be sprayed.
All in
all, it can be expected that after a 40 year service period the runway would
show only at a very few locations, traffic induced reflective cracking above
the base cracks.
4. TEMPERATURE VARIATIONS
It is a well-known fact that cementituous
materials show shrinkage cracking. For instance in the situation of a Dutch
road pavement, a cement content of 10 % by weight, implied that after 1
month, average transverse crack spacings of about 6 m could be observed in a
non-covered (fully exposed to weather conditions) stabilized layer of sand
[2]. It is obvious that depending on the climatic conditions (severity of
the winters) and the thickness of the bituminous surfacing (degree of
insulation), after a certain number of years, a reprint of the full base
crack pattern will eventually become visible in the asphalt wearing course.
The phenomenon described above has led to the
development of precracking techniques. A common practice at Schiphol is to
'produce' rectangular shaped base slabs of 3.5 by 3.5 m. Based on asphalt
mix testing results, temperature drop assessments and numerical crack
propagation studies [6], old Dutch semi-rigid pavement field experience from
the 1970's and 1980's could be extrapolated. This supported the Ooms
decision to go for a precracking distance of 4 m, which saves costs (with
respect to the 3.5 m option).
To verify the influence of temperature
variations in time, also for this type of loading, 3D-finite element
analyses were carried out. Figure 8 gives (exaggerated) deformations of a
part of the mesh which was prepared. The mesh, size 4 by 4 m, consisted in
total of 7174 elements and was first of all subjected to a uniform drop in
temperature equal to -40 °C, representing a seasonal cycle. Because of
symmetry only a central location, where four slabs come together, had to be
analyzed. The vertical edges of the mesh were fixed in the x-direction for
the x-planes and in the z-direction for the z-planes. The bottom of the
mesh, at a depth equal to 3 m below the stabilized sand, was fixed in all
directions. The stiffness of the asphaltic layers was set equal to 1000 MPa.
A shear stiffness value of 2 (N/mm)/mm2 was given to the
asphalt/base interface. The coefficient of thermal contraction of the
asphalt mixtures was set to 2.8*10-5 -/°C; the one of the cement
treated base layers to 1.0*10-5 -/°C.

Figure 8 (Exaggerated)
Deformations due to Seasonal Temperature Variation
The computed distribution of the tensile
strains along the cross-section of the asphalt just on top of the junction
of the base cracks (notches) is given in figure 9; this for precracking
distances of 3.5 m, respectively 4 m. First of all, it is clear that the
seasonal cycle primarily causes large strains at the bottom of the asphalt
layers; the distributions are certainly not uniform in depth. Furthermore,
it can be deduced that the maximum strain increases by a factor of 1.10 due
to the increased precracking distance, which is smaller than could be
expected by simply dividing the individual slab dimensions (4.0 / 3.5 ˜
1.14). Interesting to note is that an approximative analytical approach via
a two-beam model [2], would have resulted in an 'average' tensile strain
value of 0.333 % for the 3.5 m case and 0.365 % for the 4 m case. All in
all, it is clear that the asphalt strain values are within acceptable limits
[7], especially because of the application of the Thermifalt mixture.
Figure 9 Computed Asphalt
Strains Caused by Summer/Winter Movements
It is clear that not only summer/winter but
also day/night cycles occur. Figure 10 illustrates the simulated
exponentially shaped daily temperature variation; this one could be obtained
from literature [8]. In this case the stiffness of the bituminous layers was
set to 2500 MPa; the shear stiffness of the asphalt/base interface to 2
(N/mm)/mm2.
Figure 10 Simulated
Amplitude of Daily Temperature Change
The stresses in the bituminous surfacing are
presented in figure 11; this for the final phase as well as for the
construction phase of the runway. It is visible that in both phases the
largest stresses are generated at the surface. It can also be seen that
during construction, due to the limited degree of insulation, a considerably
larger degree of tension can be developed (of course only in case of bad
luck with weather conditions); this especially at the bottom of the
bituminous surfacing where later on, aircraft loading effects are also
concentrated (see figure 7)! It is obvious that this was one of the reasons
to introduce the tough (crack resistant) Thermifalt mixture.
Figure 11 Computed
Stresses in Asphalt due to Daily Temperature Variations
All in all, it can be concluded that thermal
induced reflection of cracks is within a 40 year period very unlikely to
happen.
5. UNEVEN SETTLEMENTS
Figure 12 (Exaggerated)
Pavement Deformations in case of Uneven Settlements
Figure 13 Prescribed Permanent Deformation of Subgrade

Figure 14 Computed Shear
Slip in Interface-Asphalt Layer
From the foregoing it has become clear that
even in case of (limited!) uneven settlements, no damage is introduced in
the proposed pavement structure due to the loss of shear resistance between
the upper and the lower cement treated base layer. This is due to the
presence of the thin interface-asphalt layer. The analyses have shown that
this layer itself is flexible and tough enough for this purpose. Loss of
shear resistance at the transition between the interface-asphalt layer and
both base layers is to be prevented by using an open type of mixture (20 to
25 % voids) and roughening both the stabilized sand and the
interface-asphalt before it is covered with a new layer.
6. CONCLUSIONS AND RECOMMENDATIONS
It can be concluded that for the Amsterdam
Airport Schiphol new 5th runway case, an approach consisting of
introducing existing and new top quality materials, in combination with
3D-finite element analyses on the mechanisms (traffic, temperature cycles
and uneven settlements) which can be active, has resulted into a
cost-effective airfield pavement design concept, which is interesting for
runways of busy airports, where during a long period of time maintenance
should be avoided; especially in soft soil areas. In this way it becomes
possible to optimize ('balance') semi-rigid pavement structures. In the past
these types of pavements, which consist of several asphalt layers on top of
cement treated base layers (weight percentage cement more than 8 %) were
often rejected, because the lifetime of the asphalt at and in between the
base cracks could not be 'matched'. With the current stabilization equipment
and monitoring tools, in-situ stabilization can provide an economic
(cost-effective) and reliable base for heavily loaded pavements (not only at
airfields, but also at industrial facilities). This is especially true in
delta areas along coasts, where sand and gravel can be quarried in a cheap
way or are often already available on site.
By using the current state-of-the-art personal
computers and finite element software, it is in case of big pavement
construction projects very well possible to use numerical analyses during
the design stage; this for several types of loading (traffic, temperature
variations and uneven settlements). The fact that mesh preparation is time
consuming is not a real problem, given the importance of the output. The
only things which are missing at the moment are: a) easy, semi-automatic
placement of (multiple) wheel loads and corresponding maximum stress/strain
search algorithms and b) fast and reliable iterative solvers. With respect
to a), it can be mentioned that this is needed because it is a priori
unknown what the critical loading is. Especially in case of triple gear
aircraft this can be a serious issue, because the optimum precracking
pattern of the cement treated base layers depends on this. The automatic way
of applying (multiple) loadings is required, because there are certainly not
enough skilled pavement designers available on the market to do this job,
and depending on researchers is not a solution. With respect to b), it is
clear that parametric design cases are extremely time consuming.
REFERENCES
1. Clerx J.W.,
Construction and Design of Runways, Taxiways and Aprons. Dutch Road Congress
(in Dutch), 1957.
2. de Bondt,
A.H., Anti-Reflective Cracking Design of (Reinforced) Asphaltic
Overlays, Ph.D - Thesis, Delft University of Technology, 1999.
3. Wardle, L., APSDS -
www.mincad.com.au, 1999.
4. de Bondt,
A.H., Moßig, H. and Schrader, J.G.F., Alternative Pavement Design Study
for Amsterdam Airport Schiphol 5th Runway Project (in Dutch),
2000.
5. Scarpas, A. and Kasbergen, C.,
CAPA-3D User's Manual, 1999.
6. de Bondt,
A.H., Effect of Reinforcement Properties. 4th RILEM
Conference on Reflective Cracking, Ottawa, 2000.
7. de Bondt,
A.H., Special Applications of Sealoflex Polymer Modified Bitumen,
Sealoflex World Conference Japan, 1999.
8. Jayawickrama,
P.W., Smith, R.E., Lytton, R.L. and Tirado, M.R., Development of Asphalt
Concrete Overlay Design Equations, Texas Transportation Institute, USA,
1987.